What is being built, planned or closed in and around Lindale Park, and who is leading it: the City, Harris County, TxDOT, TIRZ 21 (Hardy/Near Northside Redevelopment Authority), and Housing Alliance HTX (formerly the Houston Housing Authority).

Edit mode. Drag each pin to its real spot, then copy the text below into the PINS block.

Affects Lindale Park (9)

Inside the neighborhood or right next to it.

Streets and safety · Lindale Park

Speed cushions east of Irvington

Scheduled

Houston Public Works and Council Member Mario Castillo's office mailed residents a proposed map of speed cushions for the streets bounded by Irvington Boulevard, Hardy/Elysian, and Cavalcade north, including Robertson Street. The community feedback window has closed, and installation is scheduled to finish by the end of 2027. A partnership with Commissioner Adrian Garcia's Precinct 2 office, which provided matching funding, made it possible. A phase 2 design for streets west of Irvington is in the works but is not yet funded.

Led by the City of Houston, with matching funding from Harris County Precinct 2

SourcesHow speed cushions get approved

Card updated · Questions about this project?

Streets and safety · Lindale Park

Cavalcade Street improvements

In design

Cavalcade Street is the site of the Cool Corridor Pilot Project, part of Council District H's Resilient H climate initiative. Using community feedback, design firm SWA developed concepts for shade, art, and walkability. TIRZ 21 is starting with pilot median landscaping and walkability upgrades, adding flashing beacons, high-visibility crosswalks, curb ramps, and sidewalks at five Cavalcade intersections (Sharman, Hain, Edison, Cetti, and Robertson), plus speed cushions at Moore and Moody Streets.

Led by the Hardy/Near Northside Redevelopment Authority

SourcesTIRZ 21 agenda, Oct. 2026Resilient Cavalcade draft, Aug. 2026

Card updated · Questions about this project?

Community facilities · Lindale Park

M.D. Anderson YMCA rebuild

Permitting / Review

The YMCA of Greater Houston plans to replace its aging branch at 705 Cavalcade with a new two-story, 32,000-square-foot facility and outdoor pool. Partial federal funding is secured, and the branch will be renamed. As the YMCA prepares to break ground, TIRZ 21 is finalizing an agreement to reimburse about $250,000 for surrounding public streetscape improvements.

Led by the YMCA of Greater Houston

SourcesTIRZ 21 agenda, Oct. 2026YMCA architect request, 2025

Card updated · Questions about this project?

Highways · Trails and parks · Community facilities · Lindale Park

Hardy Toll Road extension

Tollway from I-610 into downtown

Planning / Study
Where the Hardy Toll Road extension would be elevated or below grade Side view from north to south. The roadway is elevated from I-610 south past Cavalcade Street to just south of Collingsworth Street, below grade and partly covered from there to Lorraine Street, and elevated again from Lorraine Street toward downtown. Elevated Elevated Below grade, partly covered ground level I-610 Cavalcade Collingsworth Quitman Lorraine ← North South, toward downtown →
Side view, not to scale. In HCTRA's March 2024 concept, the tollway is elevated from I-610 south to just south of Collingsworth Street and from Lorraine Street toward downtown, and below grade and partly covered ("cut and cover") between Collingsworth and Lorraine. The design may change. On the map, the thicker outline marks the elevated sections. Source: HCTRA, Hardy Downtown Connector Vision Study, March 2024, redrawn.

This project would extend the Hardy Toll Road 3.6 miles south from the I-610 North Loop into downtown Houston. In HCTRA's March 2024 concept, the tollway would be elevated toward downtown and from just south of Collingsworth Street north to I-610, and below grade and partly covered between Lorraine and Collingsworth. Alongside the highway, the Harris County Toll Road Authority (HCTRA) is planning multi-use trails, green space, and flood detention basins designed to double as neighborhood parks. The main tollway extension remains in predesign with no confirmed construction schedule.

Led by the Harris County Toll Road Authority

SourcesHCTRA: Hardy Downtown Connector

Card updated · Questions about this project?

Streets and safety · Lindale Park

Irvington Boulevard redesign

Street safety study

Planning / Study

Harris County Precinct 2 is studying safety improvements along 4.6 miles of Irvington Boulevard in Northeast Houston as part of its Reimagine corridor studies. A resident survey is open, and Community Meeting 3 takes place Wednesday, December 9, 2026, from 6 to 8 PM at HCDE Adult Education (6515 Irvington Boulevard). No design or construction funding has been announced yet.

Led by Harris County Precinct 2

SourcesIrvington Corridor Study

Card updated · Questions about this project?

Trails and parks · Lindale Park

Moody Park redevelopment plan

Planning / Study

Harris County Precinct 2 is developing a master plan for Moody Park following its transfer from the City of Houston to the County. Precinct 2 has requested a $3 million state grant for park upgrades, which will require local matching funds. TIRZ 21's nearby METRO pocket park planning is timed to follow the park plan's community engagement.

Led by Harris County Precinct 2

SourcesFriends of Moody ParkCity newsletter, Feb. 2026County agenda item

Card updated · Questions about this project?

Trails and parks · Lindale Park

Hollywood Trail

Early concept

Local advocates are proposing a multi-use trail along Little White Oak Bayou past Hollywood Cemetery to connect Woodland Park in the Heights with Moody Park, and eventually Independence Heights. Harris County Precinct 2 awarded $500,000 for feasibility studies, with construction funding expected from multiple partner agencies.

Connects to: At its south end, the coalition's draft vision links to the White Oak Bayou Greenway, which connects to the Heights Hike and Bike Trail and runs downtown to Allen's Landing and the Buffalo Bayou trail.

Led by the Hollywood Trail coalition (initial funding by Harris County Precinct 2)

SourcesHollywood Trail siteHeights Trail Partnership, Aug. 2025Friends of Woodland Park: TxDOT meetingLeader News, Oct. 2024TIRZ 21 agenda, Oct. 2026

Card updated · Questions about this project?

Trails and parks · Lindale Park

METRO pocket parks

Early concept
A mown grass lot at the corner of Fulton and English Streets beside a crosswalk, with a traffic signal, a covered bike rack with metal hoops, a wood fence and houses behind.
The Fulton and English site today: an open grass lot next to the light rail stop, with a covered bike rack. One of the three METRO-owned sites in the pocket park planning.

TIRZ 21 is planning three small parks on METRO-owned lots along the light rail line at Fulton and English, Fulton and Beggs, and Main and Boundary. Preliminary 2023 concepts envision a public art plaza, a dog park, and outdoor dining. In November 2025, the board approved up to $51,375 for conceptual planning with design firm SWA, and community outreach will run alongside the Moody Park master plan meetings.

Led by the Hardy/Near Northside Redevelopment Authority

SourcesTIRZ 21 agenda, Sept. 2025TIRZ 21 minutes, Nov. 2025TIRZ 21 agenda, Oct. 2026

Card updated · Questions about this project?

Also nearby (10)

Elsewhere on the Near Northside, in the same planning area.

Streets and safety · Trails and parks

Quitman Street improvements

Under construction

Partner agencies are rebuilding Quitman Street between Houston Avenue and Elysian Street with increased lighting, additional shade trees, and a protected two-way bike lane. The Greater Northside Management District's project page lists a completion estimated for late fall 2026.

Led by the Greater Northside Management District with Harris County Precinct 2, METRO, and the City of Houston

SourcesTIRZ 21 agenda, Apr. 2026Public meeting slides2025 construction updateGNMD: Quitman Corridor

Card updated · Questions about this project?

Trails and parks

Pinckney Trail

Under construction

Harris County is building a trail link between Fletcher and South Streets to connect neighbors to the White Oak Bayou Greenway. Two utility poles blocking the route have been moved, and the County is finalizing terms with its contractor to finish the remaining work on an updated schedule.

Led by Harris County

SourcesTIRZ 21 agenda, Oct. 2026

Card updated · Questions about this project?

Streets and safety

Northside High School area drainage and paving

Under construction

The City of Houston is leading a $48.2 million rebuild of streets and drainage around Northside High School, adding new storm sewers, concrete paving, curbs, sidewalks, driveways, and water and sewer lines. Construction began in May 2026, starting on Panama and Booth Streets, and is expected to wrap up in spring 2029.

Led by the City of Houston; funded by Harris County Precinct 2 and the City

SourcesCity project page

Card updated · Questions about this project?

Trails and parks

White Oak Bayou Greenway closure

Under construction

TxDOT closed the White Oak Bayou Greenway between Houston Avenue and the Castillo Community Center on January 15, 2026, while crews build the I-45 and I-10 connector ramps. The closure is expected to last through 2028, with occasional temporary reopenings along the way, and a marked detour is posted on site.

Led by TxDOT

Card updated · Questions about this project?

Streets and safety

Beggs and Irvington sidewalks

Scheduled

TIRZ 21 is building and repairing sidewalks along Beggs Street (Weiss to Kennon) and Irvington Boulevard (Erin to Collingsworth). The board awarded a $645,000 construction contract, with work scheduled to kick off in November 2026 and run about 92 days.

Led by the Hardy/Near Northside Redevelopment Authority

SourcesTIRZ 21 agenda, Oct. 2026TIRZ 21 agenda, Apr. 2026

Card updated · Questions about this project?

Streets and safety

Fulton paving and drainage

In design

The City of Houston plans a $7.5 million full rebuild of Fulton Street between Quitman and Hogan as a four-lane road with new storm drainage, sidewalks, curbs, lighting, and buried utilities. Curb bump-outs and upgraded signals at Quitman and Hogan will slow traffic and make walking to schools and transit safer, with construction slated for winter 2027 through winter 2029.

Led by the City of Houston

SourcesCity project pageCity engineering plans list

Card updated · Questions about this project?

Housing and development

Hays Street affordable housing

Permitting / Review

A developer plans to build 110 affordable apartments at 1500 Hays Street (including 1406 Hays). On August 20, 2026, the Planning Commission conditionally approved a replat for the 3.2-acre site (called Hays Street Reserve), though the plat must still be recorded and construction plans reviewed before building permits are issued. A state filing lists a November 2026 start and May 2028 finish, though those dates may shift.

Developer to be confirmed (LJA Engineering is the replat applicant)

SourcesState accessibility filingHAIF: 3201 Hardy St.

Card updated · Questions about this project?

Housing and development

Irvinton Village

Public housing relocation

Permitting / Review

Housing Alliance HTX is awaiting HUD approval on a plan to help current residents relocate to safer housing using housing vouchers and full moving assistance. The shift comes after draft FEMA maps placed roughly 85% of the site in the 100-year floodplain, making earlier redevelopment plans unviable. Once residents have relocated, the land will be repurposed for flood mitigation, green space, or other neighborhood improvements shaped with local partners. HUD's review runs through 2026, with moves scheduled from early 2027 into the summer if approved.

Led by Housing Alliance HTX (formerly the Houston Housing Authority)

SourcesKPRC report, May 2026HAIF: demolition thread

Card updated · Questions about this project?

Streets and safety

Hogan and Lorraine corridor study

Planning / Study

Harris County Precinct 2 and TIRZ 21 are studying safety and street improvements along 1.6 miles of Hogan and Lorraine Streets between I-45 and I-69. Preliminary design shows Hogan and Lorraine being reduced to two lanes with wide sidewalks, dedicated turn lanes at major intersections, and parking lanes. This follows two public meetings in 2025 that presented four design options, and the County is scheduling a third community meeting. Hogan is part of the City's Walkable Places pilot areas.

Led by Harris County Precinct 2, in partnership with the Hardy/Near Northside Redevelopment Authority

SourcesReimagine Hogan Street project siteTIRZ 21 agenda, Oct. 2026City: Walkable Places, Hogan/Lorraine

Card updated · Questions about this project?

Housing and development

Hardy Yards

Mixed-use development at 800 Burnett Street

Planning / Study

The Harris County Housing Finance Corporation is leading a phased mixed-use redevelopment at 800 Burnett Street, next to the Burnett Transit Center. Phase 1, led by selected partner NRP Group, plans roughly 223 affordable apartments and over 15,000 square feet of ground-floor retail, while Phase 2 calls for at least 200 more homes and 30,000 square feet of commercial space (up to 500 homes total). Construction dates have not yet been announced.

Led by the Harris County Housing Finance Corporation

SourcesHousing finance solicitationsNRP Group selected, Oct. 2025Bisnow, July 2025

Card updated · Questions about this project?

Last updated November 26, 2026. Redevelopment Authority projects come from the TIRZ 21 agenda for its October 16, 2026 board meeting. City, County, housing authority and TxDOT items come from public records, news reports and project notices. Schedules shift, so check with the agency named on each card for the latest.